We will see the processes listed below Time management knowledge area in this post.
Time management: It is a process required to ensure timely completion of the project.
Time management processes: The following are the processes of the time management knowledge area.
1) Define Activities,
2) Sequence Activities,
3) Estimate Activity Resources,
4) Estimate Activity Duration,
5) Develop Schedule, and
6) Control Schedule
1) Define Activities:
Inputs:
Scope Baseline, Enterprise Environmental Factors(EF), Organizational Process Assets (OP)
Tools and Techniques:
Decomposition, Rolling wave planning, Templates, Expert Judgment
Outputs:
Activity List, Activity Attributes, Milestone List
2) Sequence Activities:
Inputs:
Activity List, Activity Attributes, Milestone List, Project Scope Statement, Organizational Process Assets (OP).
Tools and Techniques:
Precedence Diagram Method (PDM), Dependency determination, Applying leads and lags, Schedule Network Templates
Outputs:
Project Schedule Network Diagrams, Project Document Updates
3) Estimate Activity Resources:
Inputs:
Activity List, Activity Attributes, Resource Calendars, Enterprise Environmental Factors (EF), Organizational Process Assets (OP)
Tools and Techniques:
Expert Judgment, Alternative Analysis, published estimating data, Bottom-up estimating, Project Management Software
Outputs:
Activity Resource Requirements, Resource breakdown structure, Project document updates
4) Estimate Activity Duration:
Inputs:
Activity List, Activity Attributes, Activity Resource Requirements, Resource Calendars, Project Scope Statement, Enterprise Environmental Factors (EF), Organizational Process Assets (OP)
Tools and Techniques:
Expert Judgment, Analogous estimating, parametric estimating, three point estimating, reserve analysis
Outputs:
Activity duration estimates, project document updates
5) Develop Schedule:
Inputs:
Activity List, Activity Attributes, Project Schedule network diagram, Activity resource requirements, Resource Calendars, Activity duration estimates, project scope statement, enterprise environmental factors (EF), organizational process assets (OP)
Tools and Techniques:
Schedule network analysis, critical path method, critical chain method, resource leveling, what-if scenario analysis, applying leads and lags, schedule compression, scheduling tool
Outputs:
Project schedule, schedule baseline, schedule data, project document updates
6) Control Schedule:
Inputs:
Project management plan, project schedule, work performance information, organizational process assets (OP)
Tools and Techniques:
Performance reviews, variance analysis, project management software, resource leveling, what-if scenario analysis, adjusting leads and lags, schedule compression, scheduling tool.
Outputs:
Work performance measurements, organizational process assets updates (OP), change requests, project management plan updates, project document updates.You can save it in a spread sheet to read it easily.