SDLC Phases and their I/P & O/P

Gurus,

I have listed the documents involved in all the phases of SDLC in a project below. Kindly let me know if I have missed anything in this list:

Planning Phase:
Input: Application Goals
Output: Project plan & Schedule, QA Plan, Configuration Plan

Requirement Phase:
Input: HLD (Project Plan)
Output: Requirement Document, Updated HLD Document, and Requirement Traceability Document.

Design Phase:
Input : Requirements Document
Output : Design Document, Updated HLD & Schedule, Updated Req Traceability Document

Development Phase:
Input : Design Document
Output: Software, Test Plan, Implementation Plan

Test Phase:
Input : Software, Test Plan, Implementation Plan
Output: Integrated Software, Acceptance Plan, Production Initiation plan

Installation & Acceptance Phase:
Input : Integrated Software, Acceptance Plan, Production Initiation plan
Output: Acceptance Test, Archived Project plan, Archieved Software

Am signing off here. Catch you later.
:)
C U...

4 comments:

  1. Hari,

    Please note the planning is not a phase but a process which will run concurrent to all the phases of a project lifecylce. You never do planning only once, right! Every phase of the SDLC requires planning.

    ReplyDelete
  2. You are right. I made a mistake by making it as phase. I will take care of these things in the future. Thanks for your point Ajay!

    ReplyDelete
  3. Cool article to my mind. Thanks for sharing this information.